All 27 Articles
Click an Article to open its clauses · ★ marks clauses carrying a hard number or a deadline
Project lifecycle
What falls due at each stage, from the Letter of Acceptance to the Taking Over Certificate
Key numbers
Every percentage, period and rate in the Agreement, grouped by what it governs
Maintenance payment by year
Clause 14.1(i) — percentage of the Contract Price payable each year of the Maintenance Period
Paid as a monthly lump sum of 1/12th of the annual cost (Clause 19.6), adjusted quarterly on the WPI for all commodities (Clause 19.12) and reduced for non-compliance with Schedule-E under Schedule-M.
Price adjustment component weightages
Clause 19.10(e) — the percentages that govern price adjustment of the Contract Price
Indices are taken for the month three months prior to the month to which the IPC relates, against the Base Date: WPI for construction machinery, Ordinary Portland Cement, all commodities and Mild Steel Long Products; CPI for industrial workers for labour; the nearest refinery’s retail price for bitumen; and the IOC pump price for HSD.
Who does what
Every clause sorted by the party that carries the primary obligation · click a row to open it
Schedules A to R
The 18 schedules that form part of the Agreement and the clauses that drive them
Defined terms
All 111 terms defined in Clause 1.1 — every obligation in the Agreement turns on these