EPEPCmodebyPlusBrainsDocument Navigators
MoRT&H standard documents · decoded

Highway document navigators

The two standard contracts that govern National Highway delivery in India — opened up article by article and clause by clause, with every timeline, percentage and damages figure where you can find it.

Choose a document

EPC

EPC Agreement

The Model Engineering, Procurement and Construction Agreement for road and bridge works. October 2026, with every change from the March 2019 edition marked.

28Articles
205Clauses
19Schedules
125Terms
  • Lump sum Contract Price with stage payments against Schedule-H
  • What changed from 2019 — 106 clauses changed, 8 of them new, with the old wording marked up
  • Provisional Certificate, Punch List and the 270-day Right of Way cut-off
  • Price adjustment weightages and the quarterly maintenance payment table
  • The March 2019 edition stays available alongside
Open the EPC navigator
HAM

HAM Concession Agreement

The Model Concession Agreement for Hybrid Annuity Projects — public private partnership in highway development. November 2020.

42Articles
212Clauses
19Schedules
141Terms
  • 40% paid across ten milestones, the balance as 30 biannual annuities
  • The full annuity schedule and the interest that runs on the reducing balance
  • Termination payment matrices by milestone, before and after COD
  • Independent Engineer, Escrow Account and the lenders’ substitution right
Open the HAM navigator
SPECS

Specifications for Road & Bridge Works

The MoRT&H Specifications, Sixth Revision, published by the Indian Roads Congress. 22 October 2026.

33Sections
398Clauses
220Tables
331Codes
  • Every clause and sub-clause in full text, not summarised
  • All tables extracted as real data — gradings, tolerances, acceptance criteria
  • Index of every IRC and IS code cited, and the clauses citing each
  • Search across clause text, table contents and codes at once
Open the Specifications navigator
PlusBrains

Built by PlusBrains

EPCmode is one of the tools PlusBrains builds for highway engineering teams

Make WorkFlow – Automatically. If your team spends its days on letters, bills, audits and estimates, PlusBrains can take the routine out of it.

01

Site desks for AE teams

TL Desk, AE Desk, Bill Desk and more: correspondence, progress, bills and claims for each package in one place.

02

Bill & IPC audits

Contractor bills checked line by line against the BOQ, drawings, measurements and the Agreement.

03

DPR & estimate reviews

Old-versus-new estimate comparisons, rate analysis and quantity checks, reported as clear dashboards.

04

Document navigators

Contracts and specifications opened up clause by clause — like the three on this page.

Side by side

 EPC Agreement (Oct 2026)HAM Concession Agreement
PartiesAuthority and ContractorAuthority and Concessionaire
SupervisionAuthority EngineerIndependent Engineer
Who financesThe Authority pays for the works as builtConcessionaire finances 60%, recovered as annuities
Payment basisLump sum Contract Price, stage payments per Schedule-H40% in ten milestone instalments of 4%, 60% as 30 biannual annuities over 15 years
Interest to ContractorNone on the price; 9% p.a. on delayed security releaseMCLR of top 5 banks + 1.25% on the reducing Completion Cost
Performance Security[**%] of Contract Price, set per project; e-BG or Surety Bond5% of Bid Project Cost
Additional securityAs specified in the RFP10% of the gap where the bid is over 10% below the estimate
Retention6% of each payment, capped at 5% of Contract PriceNo retention — an Escrow Account governs all flows
Scheduled Completion[**th] day from the Appointed Date, set per project550th day from the Appointed Date
Milestone damages0.25% of Performance Security per day, after a 30-day grace0.1% of Performance Security per day, after a 90-day grace
Completion delay0.25% of Performance Security per day0.2% of Performance Security per day, from the 91st day
Early bonus0.03% per day, capped at 5% of Contract Price; paid after the DLP0.5% of 60% of Bid Project Cost for the first 30 days
Mobilization advance10%, at MCLR of top 5 banks + 1.25%, compounded annually10%, at MCLR + 1.25%, compounded annually
After completionMaintenance Period, paid quarterly as a yearly percentage of Contract PriceOperation Period of 15 years, O&M Payments with the annuities
Defects liability5 years flexible or rigid, 10 years perpetual pavement and Major Bridges, 3 years riding-quality works120 days after Termination, with 15% of the last annuity retained
Change of ScopeCapped at 20% of Contract PriceNo stated cap; 2% of the bid to match a competing bidder
Price adjustmentComponent weightages on WPI, CPI, bitumen and HSDA single Price Index Multiple applied to every invoice
Force Majeure exit60 days within a continuous 120180 days within a continuous 365
DisputesAmicable settlement, then conciliation or arbitration — SAROD or IIAC for claims below Rs 10 croreIndependent Engineer, Dispute Resolution Board, Conciliation Committees, then arbitration
Delayed paymentMCLR of top 5 banks + 1.25%Bank Rate + 4%

Figures shown are those printed in the standard forms. Several — the 650th and 550th day, the 15-year Operation Period, the number of annuity instalments and the security amounts — appear in brackets in the originals and are fixed project by project in the executed agreement. Each navigator flags these where they arise.