EPEPCmodeAll agreements Ministry of Road Transport & Highways · November 2020

HAM Concession Agreement decoded
Article & clause navigator

The Model Concession Agreement for Hybrid Annuity Projects — every Article and every clause, with the payment structure, milestones, annuity schedule and termination matrices that sit behind them, searchable in one place.

6Parts
42Articles
212Clauses
19Schedules
141Defined terms
40:60Pay split

All 42 Articles

Click an Article to open its clauses · ★ marks clauses carrying a hard number or a deadline

How HAM pays

The mechanism that distinguishes Hybrid Annuity from EPC — 40% during construction, the balance as indexed annuities with interest

Construction Period — the ten Payment Milestones

Clause 23.4

Each instalment is 4% of the Bid Project Cost adjusted for the Price Index Multiple applicable on the Reference Index Date preceding the date of the Independent Engineer's report, and is disbursed within 15 days of that report. On a Change of Scope the Physical Progress is recalculated for the changed scope.

Operation Period — the 30 annuity instalments

Clause 23.6.3 — percentage of the Completion Cost remaining to be paid on COD

The thirty percentages total exactly 100%. Each instalment is paid with interest on the reducing balance of Completion Cost at the average one-year MCLR of the top 5 Scheduled Commercial Banks plus 1.25%, calculated on a simple basis with no compounding, by reference to the number of days each rate was applicable. The first instalment falls due within 15 days of the 180th day of COD, and the rest within 15 days of each successive six months.

Termination Payment by milestone

Clauses 31.3.2 and 28.9 — percentages are of the Bid Project Cost; the lower of the two bases applies

Where Termination falls between two Payment Milestones, only the milestone actually achieved counts. Each amount is reduced by the Insurance Cover; where insurance claims forming part of that cover are not admitted and paid, 80% of the unpaid claims is included in the computation of Debt Due. After COD the basis changes entirely: 65% of the unpaid annuities on a Concessionaire Default, 75% on a Non-Political Force Majeure Event.

Points to watch in the standard form

Internal inconsistencies and project-specific blanks worth knowing before you rely on a figure

Project lifecycle

What falls due at each stage, from signature to the Vesting Certificate

Key numbers

Every percentage, period and rate in the Agreement, grouped by what it governs

Who does what

Every clause sorted by the party that carries the primary obligation · click a row to open it

Schedules A to S

The 19 schedules that form part of the Agreement and the clauses that drive them

Defined terms

All 141 terms defined in Article 42 — every payment and obligation turns on these